    Here is the latest update from an official with NCDOT on both highway projects involving 194 from Valle Crucis to Banner Elk and Valle Crucis to Vilas.

    194 from Valle Crucis to Banner Elk: Work continues on retaining walls at two sites on the road, milled a portion of road to help identify possible areas to work on before paving operations begin. The newly built section in the curve just before Dutch Creek Road and Valle Crucis Mission School is on schedule to be open before the Valle Crucis Fair on Saturday October 15.

    194 from Valle Crucis to Vilas: The last culvert is set and back-filled, preparations are underway for paving and guardrail installation.